we will make a recommendation to the Board of Commissioners on October lst. A pre-conference <br />is scheduled on 10/8 and the contractor will start on 10/13. Tom's estimate is a 4-6 week <br />completion with the contractor being done by 11/21 at the latest. <br />. <br />Discussions were held on the depth of the excavation, issues pertaining to a set grade level, and <br />trying to minimize backfill. Leonard will provide Risk Management with actual elevations to <br />include in this phase of the project. The key is having a site that is financible. Remediation levels <br />will override the bacl~ill issue in order to get financing. Accurate records tracking the remediation <br />will be maintained. Remediation will be scheduled to be completed by the end of November with <br />the general contractor starting the construction phase either December 1 or January 1. We need to <br />look at other items that need to happen in order to keep the project on target as well. <br />Page 4 of 4 ~ <br />