$1,179,356.00 <br />Total Committed-Construction Change Orders $ 959,637 $ 219,719 <br />*$33,600 of COR #20 is a County only cost as it is related to the backfilling of areas that were environmentally impacted. <br />*` $16,170 of COR #51 is a County only cost as it is related to the backfilling of areas that were environmentally impacted. <br />Original Marion County Project Contingency- (Includes Remediation Contingency) $ 2,276,696 <br />Minus Change Orders (Excludes Remediation-Related CO's) $ (782,979) <br />Minus Change Orders Related to Soils Remediation $ (176,658) <br />Minus Transfers to Soft Costs $ (224,153) <br />Chanae Order Costs to be Allocated $ 11,399 <br />Total Remaining Project Contingency <br />$ 1,104,305 <br />__________________________________________________ <br />TOTAL COUNTY CONTINGENCY SPENT $ (1,183,790) <br />Contingency spent as a percentage of total County contingency ~~».~~~~~~° ?: <br />(Excludes $2M alloted to debt reduction) <br />