Laserfiche WebLink
/ <br />5.6 Subject to the provisions of tl~e Contract Documents, the amount of each progress payment shall be computed as follows: <br />5.6.1. Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percenta~e <br />canpletion of each portion of the Work by the share of the total Contract Sum allocated to that portion of the Work in the Sched ~. <br />of Values, less retainage of five percent ( 5%) . Pending final determination of cost to the Owner of changes in the Work, amounl~ <br />not in dispute may be included as provided in Subparagraph 7.3.7 of the General Conditions even tl~ough tl~e Contract Sum has not <br />yet been adjosted by Change Order; <br />5.6.2 Add that portion of tlie Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site <br />for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off tlie site at a <br />location agreed upon in writing), less retainage of percent (%); <br />5.6.3 Subtract the aggregate of previous payments made by the Owner; and <br />5.6.4 Subtract amounts, if any, €e~ ~ki~ ~ke ~sk~e~ -has rvithheld or nullified pursu~nt to a Certificate for Payment as <br />provided in Paragraph 9.5 of the General Conditions. <br />5.7 The progress payment amount determined in accordance with Paragraph 5.6 shall be furtl~er modified under the following <br />circumstances: <br />5.7.1 Add, upon Substandal Completion of the Work, a sum sufficient to increase the total payments to tti~tef~ fiv~ percent ( 95 <br />%) of the Contract Sum, less such amounts as tl~e ~TWn~~;~sk~e~ shall determine for incomplete Work and unsettled claims; and <br />5.7.2 Add, if final completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional <br />amounts payable in accordance with Subparagraph 9.10.3 of the General Conditions. <br />5.8 Reductiqn or limitation of retainage, if any, shall be as follows: <br />(7f it rs intended, prior to Su6stantlal Completion of the enNre Work, to reduce or limit the retainage resulting from the percentages inseRed in Subparagraphs 5.6.1 <br />and 5.6 2 above, and ~his is not explained e/sewhere in the Contract Documents, insert here provisions for st~ch reduction or Iimitation.J <br />n!a <br />~ <br />ARTICLE 6 <br />FINAL PAYMENT <br />Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when (1) <br />the Contract has been fiilly performed by the Contractor except for the Contractor's responsibility to oorrect nonconfornung Work as <br />provided in Subparagraph 12.2.2 of the General Conditions and to sadsfy other requirements, if any, which necessarily survive final <br />payment; and (2) a final Certificate for Payment has been issued by the Architect.~nd ~C~-tiwledg~ 'by t~te ~i~ such final <br />payment shall be made by the Owner not more than 30 days after the issuance of the Architect's final Certificate for Payment; '~ <br />as-~'e~ew~: <br />ARTICLE 7 <br />MISCELLANEOUS PROVISIONS <br />T.1 Wl~ere reference is made in this Agreement to a provision of the General Conditions or another Contract Document, the <br />reference refers to that provision as amended or supplemented by other provisions of the Contract Documents. <br />AIA DOCUMENT A101 • OWNER-CONTRACTOR AGREEMENT • TWELFTH EDITION • AIA • COPYRIGHT 1987 • THE AMERICAN INSTIT(TI'E OF <br />ARCHITECTS, 1733 NEW YORK AVENUE, N.W., WASHINGTON, D.C., 20006-5292. WARNING; Unlicensed photocopying vio(ates U.S. copyright Iaws and is <br />~b~ ~t l~e`gal prosecution. This document was electronically produoed wiUt pern~ission ofthe AIA and can be reproduced wrthout violation uMil fhe date ofexpiration r~ <br />Electronic Format A101-1987 <br />User pocument: A101 -- 2/18/1999. AIA License Number 100632, which expires on 12/7/1999 - Page #4 <br />