COR #62 8 $ 758.00 Luminar base at flagpole $ 526 $ 232
<br />COR #63 8 $ 2,310.00 Stand pipe changes per PR #3 $ 1,602 $ 708
<br />COR #64 8 $ 40,678.00 Added rebar at pour strips $ 28,214 $ 12,464
<br />COR #65 S $ (3,600.00) Delete 2' sand layer $ (2,497) $ (1,103)
<br />COR #66 8 $ 208.00 Added steel bracing at canopy $ 144 $ 64
<br />COR #67 8 $ 9,245.00 Change door frames per PR #31 $ 6,412 $ 2,833
<br />COR #68 8 $ 553.00 Owner's job shack phone S 384 $ 169
<br />COR #69 8 $ 116.00 Provide dowels at east stairwell $ 80 $ 36
<br />COR #70 8 $ 371.00 Provide thickened generator slab $ 257 $ 114
<br />COR #71 8 $ 2,201.00 Provide changes to air intake S 1,527 $ 674
<br />COR #72 8 $ (3,318.00) NTE credit on removal of three tanks $ (3,318) $ -
<br />COR #73 8 $ 5,269.00 Provide changes to column base $ 3,655 $ 1,614
<br />COR #78 8 $ 964.00 Added dowels and shear head $ 669 $ 295
<br />COR # 34 9 $ 1,607.00 Add (4) hot water hose bibs per PR #8 $ 1,115 $ 492
<br />COR # 37 9 $ 31,336.00 Provide sump pit per PR #9 $ 21,735 $ 9,601
<br />COR #75 9 $ (17.00) Provide revisions to electricai drawings per PR #16 $ (12) $ (5)
<br />COR #76 9 $ 11,157.00 Provide changes to air at rooms per PR #27 $ 7,738 $ 3,419
<br />COR #82 9 $ 726.00 Provide two additional 4" conduit sleeves in Data/Com room per PR # 29 $ 504 $ 222
<br />COR #83 9 $ 677.00 Provide two additional 1" conduits with puii cords per PR # 28 $ 470 $ 207
<br />COR #84 9 $ 8,960.00 Provide 273 3" conduit sieeves per EC proposal alternate # 32 $ 6,215 $ 2,745
<br />COR #79 10 $ 82,520.00 Removal and disposal of unsuitable subgrade material $ 57,236 $ 25,284
<br />COR # 31 11 $ - Provide modifications to public works package per City's requirements $ - $ -
<br />COR # 32 11 $ 4,607.00 Provide access hatch and revisions to plumbing and sprinkier system $ 3,195 $ 1,412
<br />COR # 46 11 $ (20,759.00) Delete bentonite waterproofing and reduce slab thickness in same area $ (14,398) $ (6,361)
<br />COR # 49 11 $ 7,278.00 Provide insulation at rebar dowels and durometer bearing pad per RFI's 199 and 204 $ 5,048 $ 2,230
<br />COR #52 11 $ 2,934.00 Provide dewatering for undocumented fill areas from 5/21/99 to 6/20/99 $ 2,035 $ 899
<br />COR #58 11 $ 1,407.00 Provide changes to gas pressure regulators per PR #21 $ 976 $ 431
<br />COR #77 11 $ - Changes to elevator beams per PR #34 $ - $ '
<br />COR #89 11 $ 387.00 Provide additional rebar at south slab step (gridline D) per structurai engineer site visit $ 268 $ 119
<br />COR #93 11 $ 855.00 Provide reinforcing at arcade slab per RFI 297 $ 593 $ 262
<br />COR #94 11 $ 2,794.00 Provide additional reinforcing and 6" hooks per submittal 2F1 and RFI 328 $ 1,938 $ 856
<br />COR #95 11 $ 5,558.00 Provide changes to nine columns per RFI 317 $ 3,855 $ 1,703
<br />COR #96 11 $ 405.00 Provide additional reinforcing for arcade beams per RFI 319 $ 28~ $ ~24
<br />COR #99 11 $ 2,139.00 Provide slab continuation at bottom of east and west shafts per RFI 236 $ 1,484 $ 655
<br />COR #102 12 $ 33,688.00 Removai and disposal of unsuitable subgrade material $ 23,366 $ 10,322
<br />COR #88 13 $ 21,567.00 Removal and disposal of contaminated soiis-359.45 c.y. S 21,567 $ -
<br />COR # 14 14 $ 1,362.00 Provide ductwork and supply fan revisions per PR #1 $ 945 $ 417
<br />COR #81 14 $ 4,607.00 Provide concrete ceiling above switch gear and revise CMU walls per RFI 193 $ 3,195 $ 1,412
<br />COR #85 14 $ 4,686.00 Provide additional conduit for swing gate operator per approved submitta102710-001 $ 3,250 $ 1,436
<br />COR #87 14 $ 877.00 Provide short wali reinforcing at parking garage lobby per RFI 160 $ 608 $ 269
<br />COR #100 14 $ 255.00 Provide changes to exit signs per PR #42 $ ~~~ $ 78
<br />COR #101 14 $ 654.00 Provide electrical power to the tower clock per RFI 233 $ 454 $ 200
<br />COR #103 14 $ 294.00 Provide changes to bridge connection detail 9/S6.1.1 per RFI 343 $ 204 $ 90
<br />COR #107 14 $ 475.00 Provide additional PT cables and reinforcing @ grid M/10b $ 329 $ 146
<br />COR #110 14 $ 7,192.00 Provide additional reinforcing ~ floors 3, 4, 5 per structural shop drawing review $ 4,988 $ 2,204
<br />COR #114 14 $ 1,574.00 Provide ductile iron for domestic and fire water service in lieu of copper per City of Saiem $ 1,092 $ 482
<br />COR # 11 15 $ 265.00 Provide door, wall and electrical revisions to second floor per PR #2 $ 184 $ 8~
<br />COR # 41 15 $ 622.00 Provide rebar to header above fire doors at parking separation wall per RFI 12 and COR #41 rev. $ 431 $ 191
<br />COR #108 15 $ 859.00 Provide changes to luminaires and electrical connections per PR #18 rev. $ 596 $ 263
<br />
|