Meeting Notes <br /> Holiday Inn express: Keizer Station <br /> Minutes of Project Meeting <br /> held <br /> 10.00 pm - Tuesday May 15, 2018 <br /> Present: Don Johnson Architect <br /> Gary Smith Project Superintendent <br /> Chris Burgess Wright Construction: Senior Project Manager <br /> Darin Bernards Wright Construction: Weather Proofing Tech. <br /> Oleg Smolyaninov Masonry Contractor <br /> Josh Rupe Dryvit Representative <br /> Purpose of meeting to discuss Masonry installation and WRB details <br /> No. Item '' Action <br /> Items <br /> 1.1 The group examined the existing exterior wall construction None <br /> and discussed the installation of the masonry. It was noted <br /> that the installation deviated from the architects plan details, <br /> specifically detail 1/A530. <br /> 1.2 It was noted by all that the approved plans called for None <br /> stainless steel through wall flashing set in a bed of sealant. <br /> the <br /> 1.3 It was noted that the contractor installed an alternate Josh Rupe will <br /> Flashing consisting of a liquid applied membrane using a Provide a <br /> product provided by Dryvit. A continuous liquid applied letter <br /> membrane was installed in lieu of more traditional felt. Stating that <br /> the <br /> It was discussed that the typical masonry flashing detail installation is <br /> called for through wall flashing. Don pointed out that the satisfactory <br /> code section 1405.4 requires flashing to be installed in such and is <br /> a manner to prevent moisture from entering the wall or to warrantable <br /> redirect it to the exterior. Flashing and weep holes are to be for use as <br /> installed in the first course of masonry above finished ground installed. <br /> level. <br /> Don Johnson <br /> Josh noted that the wall assembly was protected by the will draw up <br /> Drvyit liquid applied membrane and the transition to an as-built <br /> dissimilar materials was provided by a Drvyit flashing detail for <br /> product. Josh stated that Dryvit will warrant the products as submittal to <br /> installed and stated that water will not enter the wall. the city as a <br /> revision <br /> It was noted that there are landscape drains installed around <br /> the perimeter of the building. The drain inverts are set such <br /> that finished grade will slope to the drains from both the <br /> sidewalk and the building. The drain inverts are below the <br /> first course of masonry and weep holes. <br /> 1.4 It was observed that the masonry below the storefront had <br /> not been installed. Don requested that metal flashing be <br /> [ installed in this area. The general contractor and masonry <br /> �r contractor inspected the exposed concrete shelf and installed <br /> window assembly and agreed to install the metal flashing. <br />