Plat Tracker
Below are the current departmental tasks of this plat, and their statuses, as well as a legend to descibe each status. Click the name of the task to open its details and comments.
Department & Task | Status | Received | Completed |
---|---|---|---|
Survey - Plat Submission | Completed | 5/8/2024 | 5/8/2024 |
Concurrent Review Phase | Completed | 5/8/2024 | 11/5/2024 |
Survey - Review for Compliance O.R.S. | Completed | 6/25/2024 | 7/25/2024 |
Building Inspection - Review | Completed | 5/8/2024 | 11/5/2024 |
LDEP - Review | Completed | 5/8/2024 | 5/8/2024 |
Planning - Review | Completed | 5/8/2024 | 5/10/2024 |
Survey - Return Review Copy to Surveyor | Completed | 2/19/2025 | 3/6/2025 |
Survey - Customer Submits Mylar | Completed | 3/20/2025 | 3/20/2025 |
Planning - Sign Off | Completed | 3/20/2025 | 3/24/2025 |
Survey - Sign Off | Completed | 3/24/2025 | 3/26/2025 |
Assessor - Sign Off | Completed | 3/26/2025 | 3/28/2025 |
Assessor - Tax Collection Sign Off | Completed | 3/28/2025 | 3/28/2025 |
Clerk - Sign Off, Assign Instrument Number, and Scan | Completed | 3/28/2025 | 3/28/2025 |
Survey - Updates Point Tags | Pending | 3/28/2025 | |
Clerk - Scans Mylar | Not Started |
Below are the list of revisions that have been submitted and status changes for this plat. Revisions may delay the approval process.
Date | Department & Task | Event |
---|---|---|
5/8/2024 | LDEP - Review | Status changed to Completed |
5/10/2024 | Planning - Review | Status changed to Completed |
5/13/2024 | Building Inspection - Review | Status changed to Compliance Required |
5/13/2024 | Planning - Compile & Send Customer Notice | Status changed to Completed |
5/13/2024 | Building Inspection - Customer Response Received | Status changed to Waiting |
5/13/2024 | Planning - Compile & Send Customer Notice | Status changed to Completed |
10/30/2024 | Survey - Plat Submission | Revision received |
2/19/2025 | Building Inspection - Customer Response Received | Status changed to Completed |
2/19/2025 | Survey - Review for Compliance O.R.S. | Status changed to Completed |
2/19/2025 | Building Inspection - Review | Status changed to Completed |
2/19/2025 | Survey - Return Review Copy to Surveyor | Status changed to Pending |
2/19/2025 | Building Inspection - Review | Status changed to Compliance Required |
3/20/2025 | Survey - Customer Submits Mylar | Status changed to Waiting |
3/20/2025 | Survey - Return Review Copy to Surveyor | Status changed to Completed |
3/20/2025 | Planning - Sign Off | Status changed to Pending |
3/20/2025 | Survey - Customer Submits Mylar | Status changed to Completed |
3/24/2025 | Survey - Sign Off | Status changed to Pending |
3/24/2025 | Planning - Sign Off | Status changed to Completed |
3/26/2025 | Assessor - Sign Off | Status changed to Pending |
3/26/2025 | Survey - Sign Off | Status changed to Completed |
3/28/2025 | Assessor - Tax Collection Sign Off | Status changed to Pending |
3/28/2025 | Assessor - Sign Off | Status changed to Completed |
3/28/2025 | Clerk - Sign Off, Assign Instrument Number, and Scan | Status changed to Pending |
3/28/2025 | Assessor - Tax Collection Sign Off | Status changed to Completed |
3/28/2025 | Survey - Updates Point Tags | Status changed to Pending |
3/28/2025 | Clerk - Sign Off, Assign Instrument Number, and Scan | Status changed to Completed |
Status | Description |
---|---|
Not Started | This step cannot be processed until preceding steps are completed. |
Pending | Staff is currently working on this step. |
Completed | The plat has successfully passed this step. |
Waiting | Staff is waiting for a required item, activity, and/or information. |
Compliance Required | Customer must submit additional documentation for compliance and reevaluation. |