Case Number
MCP PLA 22-049
Instrument Number
Recording Number
Plat Status
Active
Open Date
2/27/2024
Last Revised
No Revisions
Tax Lot Number
Subdivision Name
Property Address
Property Owner
S&L Farrell/N&N Pries
Submitted Date
Index Date

Tasks for MCP PLA 22-049

Below are the current departmental tasks of this plat, and their statuses, as well as a legend to descibe each status. Click the name of the task to open its details and comments.

Department & Task Status Received Completed
Survey - Plat Submission Completed 2/27/2024 2/27/2024
Concurrent Review Phase Pending 2/27/2024
Survey - Review for Compliance O.R.S. Completed 2/27/2024 3/27/2024
Building Inspection - Review Compliance Required 2/27/2024
LDEP - Review Completed 2/27/2024 2/28/2024
Planning - Review Completed 2/27/2024 2/29/2024
Survey - Return Review Copy to Surveyor Not Started
Survey - Customer Submits Mylar Not Started
Survey - Updates Point Tags Not Started

Task and Revision History for MCP PLA 22-049

Below are the list of revisions that have been submitted and status changes for this plat. Revisions may delay the approval process.

Date Department & Task Event
2/28/2024 LDEP - Review Status changed to Completed
2/29/2024 Building Inspection - Review Status changed to Compliance Required
2/29/2024 Planning - Compile & Send Customer Notice Status changed to Completed
2/29/2024 Building Inspection - Customer Response Received Status changed to Waiting
2/29/2024 Planning - Compile & Send Customer Notice Status changed to Completed
2/29/2024 Planning - Review Status changed to Completed
3/27/2024 Survey - Review for Compliance O.R.S. Status changed to Completed
Status Description
Not Started This step cannot be processed until preceding steps are completed.
Pending Staff is currently working on this step.
Completed The plat has successfully passed this step.
Waiting Staff is waiting for a required item, activity, and/or information.
Compliance Required Customer must submit additional documentation for compliance and reevaluation.