Tasks for MCP PAR 22-012

Below are the current departmental tasks of this plat, and their statuses, as well as a legend to descibe each status. Click the name of the task to open its details and comments.

Department & Task Status Received Completed
Survey - Plat Submission Completed 6/14/2023 6/14/2023
Concurrent Review Phase Completed 6/14/2023 8/25/2023
Survey - Review for Compliance O.R.S. Completed 6/14/2023 8/25/2023
Building Inspection - Review Completed 6/14/2023 7/25/2023
LDEP - Review Completed 6/14/2023 6/14/2023
Planning - Review Completed 6/14/2023 6/15/2023
Survey - Return Review Copy to Surveyor Completed 8/25/2023 8/25/2023
Survey - Customer Submits Mylar Waiting 8/25/2023
Planning - Sign Off Not Started
Survey - Sign Off Not Started
Assessor - Sign Off Not Started
Assessor - Tax Collection Sign Off Not Started
Clerk - Sign Off, Assign Instrument Number, and Scan Not Started
Survey - Updates Point Tags Not Started
Clerk - Scans Mylar Not Started

Task and Revision History for MCP PAR 22-012

Below are the list of revisions that have been submitted and status changes for this plat. Revisions may delay the approval process.

Date Department & Task Event
6/14/2023 LDEP - Review Status changed to Completed
6/15/2023 Planning - Review Status changed to Completed
7/24/2023 Building Inspection - Review Status changed to Compliance Required
7/24/2023 Planning - Compile & Send Customer Notice Status changed to Completed
7/24/2023 Building Inspection - Customer Response Received Status changed to Waiting
7/24/2023 Planning - Compile & Send Customer Notice Status changed to Completed
7/25/2023 Building Inspection - Review Status changed to Pending
7/25/2023 Building Inspection - Customer Response Received Status changed to Completed
7/25/2023 Building Inspection - Review Status changed to Completed
8/25/2023 Survey - Review for Compliance O.R.S. Status changed to Completed
8/25/2023 Survey - Return Review Copy to Surveyor Status changed to Pending
8/25/2023 Survey - Return Review Copy to Surveyor Status changed to Completed
8/25/2023 Survey - Customer Submits Mylar Status changed to Waiting
Status Description
Not Started This step cannot be processed until preceding steps are completed.
Pending Staff is currently working on this step.
Completed The plat has successfully passed this step.
Waiting Staff is waiting for a required item, activity, and/or information.
Compliance Required Customer must submit additional documentation for compliance and reevaluation.